Coast Guard MH-65E Program Completes Low Rate Initial Production, Begins Initial Operational Test And Evaluation –CG-9

H-65 short range recovery helicopterThe Coast Guard completed Service Life Extension Program activities and an avionics upgrade on an H-65 short range recovery helicopter as part of a joint production line Dec. 18, 2018. Photo courtesy of U.S. Coast Guard.


The following is taken verbatim from the Coast Guard Acquisitions Directorate web site. 

The Coast Guard is completing the first phase of production and moving to full-rate production on concurrent Service Life Extension Program (SLEP) and avionics upgrades of the service’s H-65 short range recovery helicopters.

The avionics upgrades include reliability and capability improvements for the Automatic Flight Control System; installation of a digital cockpit display system and an upgraded digital weather/surface search radar; integration of a robust Command, Control, Communications, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) suite and modernization of the digital flight deck with Common Avionics Architecture System (CAAS), common with the Coast Guard H-60 medium range recovery helicopter and similar Department of Defense aircraft. Once the upgrades are complete, the helicopter is redesignated an MH-65E.

At the same time, the Coast Guard is completing SLEP activities to replace five major structure components – the nine-degree frame, canopy, center console floor assembly, floorboards and side panels. These mission-critical improvements are designed to extend the service life of the helicopter by 10,000 flight hours.

Work was finished Dec. 18, 2018, on the first H-65 – CG 6556 – to complete SLEP activities and the avionics upgrade in a joint production line. Termed low rate initial production (LRIP), this first phase allows the service to review and validate improvements required after the initial work on the prototype and validation/verification (CG-6587) aircraft. During this phase, Coast Guard teams discovered that the wire analysis system was not completely ready for full production. On-the-spot corrections were made to remedy the problem and rolled into the production process for future aircraft.

The avionics upgrades and SLEP are being completed at the same time to achieve schedule and cost efficiencies. The Coast Guard will also sequence the installation of new upgrade components after SLEP and programmed depot maintenance is complete, avoiding unnecessary rework that would be required if the efforts were conducted separately.

Initial Operational Test and Evaluation Begins

On Jan. 7, 2019, the H-65 Program with Commander Operational Test and Evaluation Force began initial operational and test evaluation (IOT&E) activities on two of the three aircraft that have been converted to the Echo configuration, the LRIP and validation/verification aircraft. IOT&E is the evaluation process used to demonstrate the MH-65E’s airworthiness and ensure the aircraft meets operational requirements and associated performance requirements, and is able to safely and effectively perform the Coast Guard missions prior to fleet induction.

Twenty-one ground events and 56 flights have been planned for IOT&E. There will be three test periods and one make-up test period that take place in a three-month window.

A final test report of data collected from both the operational assessment and IOT&E will be used to support a decision for the program to move into full rate production. The program anticipates an ADE-3 decision in the first quarter of fiscal year 2020.

Projected completion of the MH-65E conversion for all 98 aircrafts is fiscal year 2024.

For more information: MH-65 program page

1 thought on “Coast Guard MH-65E Program Completes Low Rate Initial Production, Begins Initial Operational Test And Evaluation –CG-9

  1. A contract issued and an update on the MH-65E conversion program
    https://www.dcms.uscg.mil/Our-Organization/Assistant-Commandant-for-Acquisitions-CG-9/Newsroom/Latest-Acquisition-News/Article/1800114/coast-guard-awards-contract-for-mh-65-helicopter-components/

    “The Coast Guard awarded a $21.3 million contract to Tyonek Manufacturing Group Inc. of Madison, Alabama, March 12 to procure 89 wiring harness packages for its MH-65 short range recovery helicopters. Once delivered, Coast Guard crews at the Aviation Logistics Center in Elizabeth City, North Carolina, will replace the wiring harnesses alongside previously scheduled work to complete Service Life Extension Program (SLEP), program depot-level maintenance and MH-65E modernization activities.
    The wire harness is the assembly of electrical cables, which provide electrical power to and transmit signals for nearly all the aircraft’s systems and subsystems. The current wiring harnesses were delivered as part of the original H-65 configuration in 1984, and replacing 100 percent of the H-65 wires will result in increased performance of the airframe’s systems and subsystems.
    The SLEP will extend the service life of the MH-65 from 20,000 to 30,000 flight hours – a 50 percent increase in service life, allowing the Coast Guard to continue H-65 operations through the fleet’s planned phase-out between 2035 and 2039.
    The MH-65 Conversion and Sustainment Program is currently in the Obtain phase of the acquisition lifecycle and is nearing the end of its initial operational test and evaluation (IOT&E) at the Aviation Training Center in Mobile, Alabama. The results from this IOT&E will be used to inform plans to move into the Produce/Deploy phase in the first quarter of fiscal year 2020.”

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s