“Light ‘Em Up With the Laser”–It Could Happen

A new capability may become an option for the Mk 38 Mod. 2 gun mount that is equipping the Webber Class Fast Response Cutters. BAE and Boeing are looking at adding a 10 Kilowatt (13 HP) laser. More here.

“The Mk 38 Mod 2 Tactical Laser System couples a solid-state high-energy laser weapon module with the operational Mk 38 Machine Gun System. The addition of the laser weapon module brings high-precision accuracy against surface and air targets such as small boats and unmanned aerial vehicles. The system also provides the ability to deliver different levels of laser energy, depending on the target and mission objectives.”

I wonder if there is a “stun” setting?

Related: MK 38 mod2, 25 mm, More Than Just a Gun

Boeing and BAE Systems have teamed up to develop the Mk 38 Mod 2 Tactical Laser System for...

(Image: BAE Systems)

Deepwater program “Unachievable”–GAO, Part Two

As I noted in part one, GAO has found the Coast Guard’s Deepwater program “unachievable.” Basically, they see a mismatch between the historic funding levels and the anticipated funding requirements. This in turn has impacted the delivery schedule, which in turn further adversely effects cost. Additionally significant questions still remain regarding the C4ISR (Command, Control, Communications, Computers, Intelligence, Surveillance, and Reconnaissance) system that was intended to tie the “system of systems” together. There also remains a significant unknown in the form of the Offshore Patrol Cutter (OPC) which, as the most costly single system in the program, constituted a third of the total “Deepwater” Program’s estimated cost in the 2007 Baseline.

I’m not sure I would call that “unachievable,” rather it is simply more expensive and more difficult than the Coast Guard was lead to believe, and four years later the plan is already well out of date. The Cost overruns are significant, but no more so than a lot of procurements and pale in comparison to the F-35 and Littoral Combat Ship cost overruns.

Costs

This is the cost growth GAO has seen. From Table 2 (page 12), “Increased Total Acquisition Cost Estimates for Deepwater Assets with approved baselines as of May 2011 (Then year dollars in millions)”:

Asset                                                    2007 Baseline                Revised Baseline                 % Change

NSC                                                             3,450                                 4,749                                  38
FRC                                                             3,206                                 4,243                                  32
OPC                                                             8,098                         Not yet revised                         —
Cutter Small Boats                                       110                          Not yet revised                         — (see b. below)
MEC Sustainment                                        317                                       321                                    1
Patrol Boat Sustainment                             117                                       194                                 66
MPA                                                             1,706                                  2,400                                  41
C-130J                                                               11                                       176                             1,500 (see c. below)
C-130H                                                            610                                      745                                  22
HH-65                                                             741                                    1,242                                  68 (see d. below)
HH-60                                                             451                                       487                                    8
UAS (unmanned air system)                     503                           Not yet revised                         —
C4ISR                                                            1,353                                   2,522                                  86
Other Deepwater                                        3,557                           No revision expected              — (see e. below)
—————————————————————————————————————————————————–
Total                                                           24,230                                   29,347                                21

There were some notes with this, including some that explained some of the increased costs:

If the revised baselines present both threshold costs (the maximum costs allowable before a
breach occurs) and objective costs (the minimum cost expected), threshold costs are used. An
acquisition program baseline breach of cost, schedule, or performance is an inability to meet the
threshold value of the specific parameter.

a. When a revised baseline is not available, the 2007 baseline cost is carried forward for calculating
the total revised baseline cost.

b. The cutter small boat program includes two different versions of small boats. Only one had an
approved revised baseline as of May 2011.

c. The acquisition costs are related to the mission system. The original HC-130J baseline only included
costs associated with the fleet introduction of missionized aircraft and did not include the cost of
acquiring the mission system and logistics support of the first six aircraft, and the revised baseline
corrected this omission.

d. The 2007 approved baseline did not include airborne use of force, National Capital Region Air
Defense, and the surface search radar for the HH-65. The addition of these capabilities constitutes
about $420 million of the revised costs.

e. Includes other Deepwater costs, such as program management, that the Coast Guard states do not
require a new baseline.

Additional note from page 13, “The original 2007 estimate for one OPC was approximately $320 million. However, the Coast Guard’s fiscal years 2012-2016 capital investment plan cites a planned $640 million in fiscal year 2015 for the lead cutter. Coast Guard resource and acquisition directorate officials stated that this $640 million is a point estimate for the lead cutter, some design work, and project management”

If we look at only the programs that have had revised baseline (these make up 64% of the 2007 baseline), the cost growth has actually been 33% and even that cost is not really reliable since, in some cases, prices have increased since the revised baseline. The true cost of the eight NSCs for which good cost information is now available is expected to be approximately $5.6B, a 62% increase over the 2007 baseline. There is also still considerable uncertainty about the final cost of the unmanned air systems and the C4ISR systems.

Scheduling

The second dimension that GAO regards as unachievable is projected delivery schedule. Figure 3 on page 16 shows scheduled deliveries of the final item in each of the several projects, as originally scheduled in the Baseline document approved in 2007, as approved in subsequent baseline revisions, and as projected in the FY2012-2016 Capital Investment Plan (CIP) and the projected delay, comparing the 2007 baseline and the 2012-2016 CIP. Because the projected costs exceed likely funding, they believe that even the FY2012-2016 Capital Investment Plan schedule is “unachievable.”

Asset                                                    2007 Baseline    Revised Baseline      2012-2016 CIP     Projected Delay (years)
—————————————————————————————————————————————————–
NSC                                                              2014                        2016                       2018                            4
FRC                                                              2016                        2021                       2022                            6
MEC Sustainment                                    2016                        2017                       2014                     (2 years early)
Patrol Boat Sustainment                         2013                        2014                           —                               ?
MPA                                                            2016                        2020                      2025                             9
C-130J                                                        2009                        2011                       2011                              2
C-130H                                                       2017                         2017                       2022                             5
HH-65                                                        2013                        2020                      2020                             7
HH-60                                                       2019                        2020                      2020                              1
C4ISR                                                        2014                        2027                       2025                             11
OPC                                                            2021                          —                          2031                              10
—————————————————————————————————————————————————–

You might note that the Cutter boats and Unmanned Air Systems are not included in this table.

Capabilities

Beginning on page 30 the study notes, “Key Decisions Remain for Assets in Design to Ensure Promised Capabilities Are Achieved.”

The primary technical risk appears to be the C4ISR system which was to tie the “system of systems” together and allow the service to perform the missions with few (but more capable) assets. The CG has apparently already backed away from the concept of providing all units a common operational picture. The all singing, all dancing NTDS with pictures now appears both unnecessary and too expensive. The additional overhead in maintaining classified material may also a consideration. What the Coast Guard will ultimately choose was undecided when the study was written.

By far the largest chunk of  “Deepwater” AC&I money is expected to go for the twenty-five Offshore Patrol Cutters (OPC). “DHS approved the OPC’s requirements document in October 2010 despite unresolved concerns about three key performance parameters—seakeeping, speed, and range—that shape a substantial portion of the cutter’s design. For example, DHS questioned the need for the cutter to conduct full operations during difficult sea conditions, which impact the weight of the cutter and ultimately its cost. The Coast Guard has stated that limiting the ability to conduct operations during difficult sea conditions would preclude operations in key mission areas. While it approved the OPC requirements document, DHS at the same time commissioned a study to further examine these three key performance parameters. According to Coast Guard officials, the study conducted by the Center for Naval Analysis found that the three key performance parameters were reasonable, accurate, and adequately documented.”–That is the good news–The GAO again took the CG to task because it has not completed a Fleet Mix Study that can be used for determining trade-offs (page 45/46), but noted that DHS is doing one that includes an updated 270 and the Littoral Combat Ship as alternatives.

The report talks about a number of remaining issues, some of which have already been corrected, some of which sound like typical teething problems for new systems. One that does bother me is that the helo haul down and traversing system referred to as “ASSIST,” has been found unsatisfactory. The CG, having already bought four systems and equipping one helicopter, is now looking at the system the Navy uses (p. 40). I’m a bit surprised we didn’t go to the Navy system first for the sake of commonality.

Conclusion

The Deepwater systems are not “unachievable” in the literal sense. The question remains, will it be pursued? and will it be pursued in a reasonably expeditious fashion?

The decision to “outsource” to ICGS (Integrated Coast guard Systems) was a mistake, but it was what the government was encouraging at the time. The 2007 baseline was the best the CG could do at the time, but it was inevitably flawed having been tainted by the “puffing” of contractors who were at best overly optimistic.  Actual costs have exceeded estimates but they are not out of line compared to similar DOD programs. As I understand it, the Coast Guard engineering staffs had been gutted in previous economy moves so it is not surprising they did not get it 100% correct first try. To hold the CG to the 2007 baseline is simply unrealistic. The Question remains, does the nation want the CG to have a presence in the offshore regions? The Navy is shrinking and will not fill that void.  Dragging out the procurement will only result in higher prices in the end.

Related:

Deepwater program “Unachievable”–GAO, Part One

The GAO has issued a status report on the Coast Guard’s “Deepwater” programs. The Navy Times has a pretty good summary. (Note the Coast Guard has requested that the “Deepwater” designation be dropped, but it had not happened when the report was issued.)

Based on the the GAO report, we can expect that the programs will both cost more and take longer than planned. In fact these two problems appear to be mutually reinforcing. Because the costs are higher, the schedule is stretched out. Because the schedule is stretched out, the cost goes up.

Illustration below: The plan–six years ago

https://i0.wp.com/www.uscg.mil/ACQUISITION/deepwater/congressional/baseline.jpg

You can see the entire GAO report (pdf format) here. Below is the GAO’s own summary of the report taken from the “recommendations” page associated with this report on their web site.

“The Deepwater Program includes efforts to build or modernize ships and aircraft, including supporting capabilities. In 2007, the Coast Guard took over the systems integrator role from Integrated Coast Guard Systems (ICGS) and established a $24.2 billion program baseline which included schedule and performance parameters. Last year, GAO reported that Deepwater had exceeded cost and schedule parameters, and recommended a comprehensive study to assess the mix of assets needed in a cost-constrained environment given the approved baseline was no longer feasible. GAO assessed the (1) extent to which the program is exceeding the 2007 baseline and credibility of selected cost estimates and schedules; (2) execution, design, and testing of assets; and (3) Coast Guard’s efforts to conduct a fleet mix analysis. GAO reviewed key Coast Guard documents and applied criteria from GAO’s cost guide.

“The Deepwater Program continues to exceed the cost and schedule baselines approved by DHS in 2007, but several factors continue to preclude a solid understanding of the program’s true cost and schedule. The Coast Guard has developed baselines for some assets that indicate the estimated total acquisition cost could be as much as $29.3 billion, or about $5 billion over the $24.2 billion baseline. But additional cost growth is looming because the Coast Guard has yet to develop revised baselines for all assets, including the OPC–the largest cost driver in the program. In addition, the Coast Guard’s most recent capital investment plan indicates further cost and schedule changes not yet reflected in the asset baselines, contributing to the approved 2007 baseline no longer being achievable. The reliability of the cost estimates and schedules for selected assets is also undermined because the Coast Guard did not follow key best practices for developing these estimates. Coast Guard and DHS officials agree that the annual funding needed to support all approved Deepwater baselines exceeds current and expected funding levels, which affects some programs’ approved schedules. The Coast Guard’s acquisition directorate has developed action items to help address this mismatch by prioritizing acquisition program needs, but these action items have not been adopted across the Coast Guard. The Coast Guard continues to strengthen its acquisition management capabilities, but is faced with several near-term decisions to help ensure that assets still in design will meet mission needs. For example, whether or not the planned system-of-systems design is achievable will largely depend upon remaining decisions regarding the design of the command and control system. Important decisions related to the affordability, feasibility, and capability of the OPC also remain. For those assets under construction and operational, preliminary tests have yielded mixed results and identified concerns, such as design issues, to be addressed prior to initial operational test and evaluation. The Coast Guard is gaining a better understanding of cost, schedule, and technical risks, but does not always fully convey these risks in reports to Congress. As lead systems integrator, the Coast Guard planned to complete a fleet mix analysis to eliminate uncertainty surrounding future mission performance and produce a baseline for Deepwater. This analysis, which the Coast Guard began in 2008, considered the current program to be the “floor” for asset capabilities and quantities and did not impose cost constraints on the various fleet mixes. Consequently, the results will not be used for trade-off decisions. The Coast Guard has now begun a second analysis, expected for completion this summer, which includes an upper cost constraint of $1.7 billion annually–more than Congress has appropriated for the entire Coast Guard acquisition portfolio in recent years. DHS is also conducting a study to gain insight into alternatives that may include options that are lower than the program of record for surface assets. A DHS official stated that this analysis and the Coast Guard’s fleet mix analysis will provide multiple data points for considering potential changes to the program of record, but Coast Guard officials stated they have no intention of examining fleet mixes smaller than the current, planned Deepwater program. GAO is making recommendations to the Department of Homeland Security (DHS) that include identifying trade-offs to the planned Deepwater fleet and ensuring the Offshore Patrol Cutter (OPC) design is achievable and to the Coast Guard that include identifying priorities, incorporating cost and schedule best practices, increasing confidence that assets will meet mission needs, and reporting complete information on risks to Congress in a timely manner. DHS concurred with the recommendations.”

For those of you who don’t want to wade through the entire report, I’ll be revisiting this topic to highlight GAO’s reservations regarding costs, scheduling, and capabilities.

 

“Crisis in the Cutter Fleet”–Protecting America’s Ocean

Good to be seeing some public discussion of the Coast Guard’s need for new cutters.

This article appearing in the San Francisco Examiner was written by James Jay Carafano of the Heritage Foundation. (I think I saw virtually the same article appeared in other newspapers as well.)

The Naval Institute has published a good article explaining the need for recapitalization of the Cutter Fleet. It is available on line here. The article was writen by Captain Fears. Here is his bio from the article:

“Captain Fears is the U.S. Coast Guard’s chief of law enforcement. He has more than a decade of sea service in seven ships around the world, and he served as commanding officer in two of them. He is also the chairman of the U.S. Naval Institute Editorial Board.”

He does an excellent job of emphasizing the expansiveness of the areas to be patrolled.

Fleet Mix–Where are the Trade-Offs?

A recent GAO report offers some insight into how the AC&I budget will work for the next few years. The report is accessible here: Coast Guard: Observations on Acquisition Management and Efforts to Reassess the Deepwater Program
GAO-11-535T, Apr 13, 2011
Quick View Quick view toggle Summary (HTML)   Highlights Page (PDF)   Full Report (PDF, 18 pages)   Accessible Text

The thrust of the report seems to be that while the coast Guard has made some progress in managing its own programs since terminating Deepwater there are still a lot of problems and many of them stem from being unrealistic about budget expectations. There also seems to be an underlying frustration because the Coast Guard is not offering real alternatives to the fleet mix proposed by the discredited “Deepwater” program.

“We reported in 2009 that the administration’s budget projections indicated that the DHS annual budget was expected to remain constant or decrease over the next decade. When the Coast Guard submitted its fiscal year 2012 budget request, it also released its fiscal years 2012-2016 acquisition capital investment plan. In reviewing this plan, we found that the Coast Guard’s projected funding levels for fiscal years 2013 through 2016 are significantly higher than budgets previously appropriated or requested and therefore may be unrealistic. This unrealistic acquisition budget planning exacerbates the challenges Coast Guard acquisition programs face. As seen in figure 2, the average annual budget plan from fiscal year 2012-through fiscal year 2016 is about $520 million, or approximately 37 percent, higher than the average Coast Guard acquisition budgets previously appropriated or requested during the past 6 years.”

Continue reading

UAVs, Let’s Try This One

Here is a UAV that is already in use by the Navy. The ScanEagle, is so small it could operate routinely from the Webber Class WPCs.

Wing Span 10.25 ft (3.12m)
Length 6.5 ft (1.98m)
Max Take Off Weight 44-48.5 lb. (22 kg)
Max speed 80 knots
Cruise speed 50 knots
Ceiling 10,000 ft
Max endurance: 15 hours

In it’s “dual bay” configuration the sensor package can include a synthetic aperture imaging radar in addition to video. It can use standard diesel fuel, but it won’t use much since the engine is less than two horsepower.

It was reportedly used during the Maersk Alabama piracy incident in April 2009 (the first of three times pirates attempted to take the ship).

I think its worth a closer look, like perhaps a deployment on a 210.

https://i0.wp.com/upload.wikimedia.org/wikipedia/commons/b/b1/ScanEagleIraq.jpg

Continue reading

Multiple crewing for Fast Response Cutters

If you are a regular reader of the posts here, you know that I have not been a fan of the “Crew Rotation Concept” that is supposed to make up for the fact that we are only building eight NSC to replace twelve Hamilton Class WHECs by home-porting three ships together and providing four crews. (Previous posts on this here and here.)

One of my criticism has been that if multiple crewing is such a good idea, we should be trying it on smaller, simpler ships first. This got me thinking about how it might work for the Fast Response Cutters (FRC), and I’ve come up with a bit different concept. It may offer some advantages and there may be good reasons to try it

WPC Kathleen_Moore

Continue reading

Budget Realities Setting In?

The Marine Log is reporting “House Coast Guard and Maritime Transportation Subcommittee Chairman Frank LoBiondo (R-N.J.) set a no-nonsense tone when he opened up a hearing yesterday to review the Administration’s budget requests for the U.S. Coast Guard…’Congress must make extremely difficult decisions in the coming months to bring our spending under control and cut the deficit’…Chairman LoBiondo commended the service for uncovering some savings through efficiencies in operations and the consolidation of services, but wanted to know ‘if more operational savings can be found that will not adversely impact safety, security, and mission success.'”

He called the Coast Guard’s  five year Capital Improvement Plan “fantastic,” (not in a good way, as in, it is a fantasy) referring to a planned 66 percent increase in funding over the next three fiscal years. (Assuming we are talking about a 66% increase in AC&I over the FY2012 request ($1.4B) that is a $924M increase annually, approximately a 9% increase in the total budget.)

He also took the service to task for its failure to complete a “fleet mix analysis” that the Subcommittee requested over 13 months ago.  “I urge the Service, in the strongest possible terms, to satisfy our request for this document in short order…Second, the Service continues to lack the polar missions plan long sought by Congress. To add insult to injury, the Service intends to spend millions of unbudgeted dollars to refurbish the POLAR SEA’s engine and then decommission the icebreaker.  This is a classic example of throwing good money after bad.”

The Coast Guard is still projecting procurement planned under the discredited “Deepwater” program, almost ten years ago, that included replacing 12 WHECs with 8 multi-crewed National Security Cutters (NSC) and replacing 29 WMECs with 25 Offshore Patrol Cutters (OPC), a reduction of 20% in the number of hulls. Meanwhile, there is little evidence to prove multiple crewing of NSCs will work; UAVs, which don’t seem to be working out for reasons beyond Coast Guard control, were supposed to do a lot of the air surveillance work; drug runners are turning to semi-submersibles and true submarines that are increasingly hard to detect; and new responsibilities are coming with the opening of the Arctic to commerce. It is also possible to make a case that the South Pacific EEZ was never adequately policed. Things have changed and they justify more, not fewer assets. Continue reading

Fast Response Cutter Photos

The Cutterman facebook page has published some more photos of the Fast Response Cutter Webber (and possibly a bow on view of a follow-on ship). Unfortunately they are all taken from low on the starboard bow or directly on the bow so we don’t get views of the whole ship. Look forward to seeing the vessel emerge from the building shed and seeing the whole vessel.