Reviewing the Status of Cutter Procurement

Belatedly, I have taken a look at the July 6, 2018 edition of the Congressional Research Service’s Naval Expert, Ronald O’Rourke’s Coast Guard Cutter Procurement: Background and Issues for Congress. It was published less than seven weeks after the previous edition.

Thought perhaps a short review of the status of the three programs addressed might be welcome.

NSC: The program of record was eight ships, but eleven ships have been funded through FY2018. Six have been commissioned. One additional delivery is expected each year, 2018, 2019, 2020 and presumably 2021 and 2022. The Senate sub-committee has expressed its intention to procure a twelfth NSC, but the FY2019 budget request did not include funding for an addition NSC. FY2020 would not be too late to fund NSC#12 and keep the delivery schedule at one per year.

OPCstarboardbow

OPC: The program of record is for 25 ships. The First ship was funded in FY2018. The Second ship is in the FY2019 budget request along with long lead time items for OPC#3. If all contract options are exercised, we should see one ship delivered each year 2021, 2022, and 2023. Beginning in 2024 the program anticipates delivery of two ships per year. If they hold to that modest rate, as planned, the last OPC will not be delivered until at least 2033 at which time the newest 270 will be 42 years old. Also at that rate, the newest 210 will be 60 years old when presumably, the last of the class is replaced in 2029. (If you think keeping 40 and 50 year old cutters operational is challenging, wait until you try a 60 year old. Particularly since the Coast Guard plans no major life extension work on the 210s.) 

FRC: The program of record is for 58 vessels. There is also a requirement for six more to replace the six Island class 110 foot cutters currently homeport in Bahrain as part of PATFORSWA, that are not included in the program of record. 50 Webber class have been funded through FY2018, with 28 currently in commission. Funding for four additional vessels was included in the FY2019 budget request. The Coast Guard is commissioning Webber class at the rate five vessels annually. The remaining 28 vessel will presumably be commissioned by 2024. Six additional for PATFORSWA would extend that through 2025. Apparently the Congress intends the DOD to fund the six that would go to FATFORSWA so presumably the last Coast Guard funding would be in the FY2020 budget.

If my understanding is correct, it is likely that major funding for the NSC and FRC programs will be complete in FY2020, the same year the third OPC should be funded. At some point, in the not too distant future, we will need to start the process of replacing the 87 foot WPBs, but hopefully we will find a way to accelerate the OPC procurement to something more than two a year.

Photo Journal: RDC Arctic Technology Evaluation 2018

USV&drone

RDC researchers test the effectiveness of pairing the USV and the Splash Drone on a mission. U.S. Coast Guard photo by Alexandra Swan.

The Acquisitions Directorate (CG-9) web site is running a series to show the R&D Centers activities in the Arctic.

The Coast Guard Research and Development Center is conducting its annual operation in the Arctic, Arctic Technology Evaluation 2018, in Prudhoe Bay, Alaska, July 21 to Aug. 3. This year’s research will focus on evaluating how unmanned aircraft systems (UAS), unmanned surface vehicles (USV) and an aerostat balloon can work together as a network, and includes search and rescue and environmental mission scenarios.

“New Coast Guard Leader Focusing on Readiness”–National Defense

File:Adm. Karl L. Schultz.jpg

National Defense Magazine reports and interview with the new Commandant, Admiral Karl L. Schultz.

These two paragraphs pretty much sum up his stance.

““My intention would be to not deviate too much,” he said. “Obviously, every change brings some different thinking, different ideas, but at our core it’s … steady as you go with trying to pick up speed a little bit.”

“As part of his guiding principles over the next four years, Schultz — who took over in June — said he is focusing on making the Coast Guard a ready, relevant and responsive service.”

He intends to push readiness in terms of operating budget.

“While the service is replacing many of its aging assets, it still has 50-year-old cutters in operation, he noted. Those vessels are expensive to maintain and the newer ships coming down the pipeline will be costly as well, he added.”

Of the new cutters, only National Security Cutters look like they might actually cost less to run than the vessels they replace, based on their smaller crew, but even that is questionable. The Webber class and the Offshore Patrol Cutters are much larger, more powerful, and have larger crews than the 110s and WMECs they will replace. While we may end up with fewer NSCs than 378s (10 v 12) and fewer OPCs than WMEC (25 v 28) it looks like we will have substantially more FRCs than 110s (only 41 WPB 110s were operational when the FRC program began and it looks like we will get at least 58).

The piece goes on to discuss icebreakers and the “waterways commerce cutter” (inland tenders). Additionally, don’t expect any change in the Coast Guard’s commitment to drug interdiction, “…we’re all in.”

Officer Promotion System Gets a Make-Over

MilitaryTimes is reporting Congress is expected to authorize much greater flexibility in the Officer promotion system.

Specifically, the changes would include:
  • Ending some of the up-or-out rules that force officers to leave military service if they fail to be promoted along rigid timelines.

  • Allowing for mid-career civilians with high-demand skills to enter the military up to the rank of O-6.

  • Allowing promotion boards to move high-performing officers higher on the promotion list regardless of their time in service.

  • Allowing service secretaries to create “an alternative promotion process” for specific career fields.

None of this is mandatory, but it will give the services more options for Officer Personnel Management.

We will have to wait and see if application of the new latitude will be for good or evil.

Report to Congress on U.S. Coast Guard Polar Icebreaker Program, July 9, 2018

USCGC Polar Star. An old USCG photo, note the HH-52.

The Congressional Research Service has issued a new edition of its Report to Congress on U.S Coast Guard Polar Icebreaker Program by specialist in naval affairs Ronald O’Rourke, this one dated July 9, 21018. You can see it here. 

I have reproduced the summary immediately below.  

The Coast Guard polar icebreaker program is a program to acquire three new heavy polar icebreakers, to be followed years from now by the acquisition of up to three new medium polar icebreakers. The Coast Guard wants to begin construction of the first new heavy polar icebreaker in FY2019 and have it enter service in 2023. The polar icebreaker program has received about $359.6 million in acquisition funding through FY2018, including $300 million provided through the Navy’s shipbuilding account and $59.6 million provided through the Coast Guard’s acquisition account. The Coast Guard’s proposed FY2019 budget requests $750 million in Coast Guard acquisition funding for the program.

The acquisition cost of a new heavy polar icebreaker had earlier been estimated informally at roughly $1 billion, but the Coast Guard and Navy now believe that three heavy polar icebreakers could be acquired for a total cost of about $2.1 billion, or an average of about $700 million per ship. The first ship will cost more than the other two because it will incorporate design costs for the class and be at the start of the production learning curve for the class. When combined with the program’s $359.6 million in prior-year funding, the $750 million requested for FY2019 would fully fund the procurement of the first new heavy polar icebreaker and partially fund the procurement of the second.

The operational U.S. polar icebreaking fleet currently consists of one heavy polar icebreaker, Polar Star, and one medium polar icebreaker, Healy. In addition to Polar Star, the Coast Guard has a second heavy polar icebreaker, Polar Sea. Polar Sea, however, suffered an engine casualty in June 2010 and has been nonoperational since then. Polar Star and Polar Sea entered service in 1976 and 1978, respectively, and are now well beyond their originally intended 30-year service lives. The Coast Guard has used Polar Sea as a source of spare parts for keeping Polar Star operational.

A Department of Homeland Security (DHS) Mission Need Statement (MNS) approved in June 2013 states that “current requirements and future projections … indicate the Coast Guard will need to expand its icebreaking capacity, potentially requiring a fleet of up to six icebreakers (3 heavy and 3 medium) to adequately meet mission demands in the high latitudes….”

The current condition of the U.S. polar icebreaker fleet, the DHS MNS, and concerns among some observers about whether the United States is adequately investing in capabilities to carry out its responsibilities and defend its interests in the Arctic, have focused policymaker attention on the question of whether and when to acquire one or more new heavy polar icebreakers as replacements for Polar Star and Polar Sea.

On March 2, 2018, the U.S. Navy, in collaboration with the U.S. Coast Guard under the polar icebreaker integrated program office, released a request for proposal (RFP) for the advance procurement and detail design for the Coast Guard’s heavy polar icebreaker, with options for detail design and construction for up to three heavy polar icebreakers.

Issues for Congress for FY2019 for the polar icebreaker program include, inter alia, whether to approve, reject, or modify the Coast Guard’s FY2019 acquisition funding request; whether to use a contract with options or a block buy contract to acquire the ships; whether to continue providing at least some of the acquisition funding for the polar icebreaker program through the Navy’s shipbuilding account; and whether to procure heavy and medium polar icebreakers to a common basic design.

Coast Guard Kicks Off Arctic Technology Evaluation 2018–Acquisitions Directorate

Members of the Coast Guard Research, Development, Test and Evaluation Program (CG-926) and the Research and Development Center are in Prudhoe Bay, Alaska, to test usage of unmanned systems in the Arctic in Arctic Technology Evaluation 2018. U.S. Coast Guard photo by Alexandra Swan.

The following is a quote from the Acquisitions Directorate (CG-9) Web Site:

Coast Guard Kicks Off Arctic Technology Evaluation 2018

July 25, 2018

The Coast Guard is conducting its 2018 Arctic Technology Evaluation July 21-Aug. 3, 2018, in Prudhoe Bay, Alaska.

This year’s Arctic research will focus on evaluating how unmanned aircraft systems (UAS), unmanned surface vehicles (USV) and an aerostat balloon can work together as a network. The Coast Guard’s Research, Development, Test and Evaluation (RDT&E) Program and Research and Development Center (RDC) are partnering with Alaska Clean Seas for this year’s activities.

The research team will conduct a number of search and rescue and environmental testing scenarios, including using the unmanned systems to detect a life raft and evaluating capabilities to detect and sample a simulated oil spill. The unmanned systems will be integrated with Persistent Systems Man Pack Unit 5 radios (MPU5) to test the potential communication relay. The research team will also compare UAS sensor performance at high latitudes with data gathered through the RDT&E Program’s Robotic Aircraft Sensor Program for Maritime.

For more information: Research, Development, Test and Evaluation Program page and Research and Development Center page

Original Music for the Coast Guard

Saw this on Facebook. Michael Harrington shared a link to the group: U.S. Coast Guard Retired. It was a year ago, but it resurfaced and thought I would pass it along. Below is the information that accompanied the video on YouTube.

An original musical and visual tribute to the Coast Guard written by Coast Guard veteran, singer/songwriter, Brad Fitch, Estes Park, Colorado. Music and photos © 2011 Brad Fitch. All rights reserved. Produced by Summertown Studios, Fort Collins, CO http://www.SummertownStudios.com Bob Buford, Producer

Rep. Courtney: U.S. Needs Comprehensive National Maritime Strategy Soon–USNI

A sailor explains the layout and functionality of Ford’s flight deck to Rep. Joe Courtney in 2016. US Navy Photo

The US Naval Institute news service reports the comments of Representative Joe Courtney (D-Conn) regarding the Nations lack of a comprehensive Maritime Strategy. He is apparently mostly talking about building more submarines in his home district.

There are a couple of points I think might be worth discussing that were brought up at the end of the post.

Asked if there were plans to build new icebreakers to compete with Russia and others who are moving into the Arctic, Courtney said the Seapower panel does not deal with the Transportation Department programs (emphasis applied–Chuck), which include the Coast Guard and its icebreakers. But he said they have encouraged the Navy to cooperate to help the Coast Guard get the icebreakers it needs.

However, he added, they just heard that in the 2019 appropriations bill, the Transportation Department “gets no money for icebreakers. Some of us will want to work on that.”

First, the fact that there is no money in the 2019 budget for icebreakers.

Second, that the Seapower Sub-Committee does not deal with Coast Guard programs, seems to be part of the problem. The Coast Guard has become an increasingly important part of American Sea power. The Coast Guard is the defacto low mix in American naval power’s high-low mix. We have virtually all the patrol boats. The Coast Guard now has about one eighth the number of personnel of the US Navy. It has more personnel than either the British or French Navies. That the Seapower subcommittee does not have the opportunity to consider relative low marginal cost add-ons that could significantly increase the military value of cutters (and perhaps aircraft) is a lost opportunity.

It seems the Navy does not want to look to the Coast Guard for any significant role in a major conflict, even though the need for additional ASW assets is abundantly clear. Maybe they think a stronger, more militarily competent Coast Guard would divert money from Navy programs. Maybe they are just deferring to the Coast Guard, “Well what do you want to do?” The Coast Guard does not seem to have much of a clue what they will do in the next major, war because their platforms are not equipped to do much in the way of military missions. Hopefully there is really more coordination and planning than is evident looking in from the outside, but given our history, I doubt it.

Note, we do have A Cooperative Strategy for 21st Century Seapower: Forward, Engaged, Ready,” but it is a strategy for maintaining the peace, not a strategy for maintaining Maritime dominance, which requires a healthy shipbuilding industry and merchant marine.

Having a healthy shipbuilding industry and a healthy merchant marine seem to be at odds. The merchant marine needs cheaper ships and cheaper crew costs, both likely to happen only if we allow some foreign shipbuilding and some foreign crewmen. A healthy shipbuilding industry seems to require buying ships made in America at costs above the going international rate. Some Western Countries seem to have cracked to code on how to have both high wages and healthy shipbuilding and merchant marines. Some of that is due to subsidies. I wish our leadership luck in coming up with a good maritime strategy. We did it once, during the run-up to WWII, and it may have saved the world from tyranny.  

(Sorry about the rant, is my frustration showing?)

 

Coast Guard Releases Request For Information For Polar Star Service Life Extension Project

The following is a quotation in full of a post from the Acquisition Directorate (CG-9)

Coast Guard Releases Request For Information For Polar Star Service Life Extension Project

July 19, 2018

The Coast Guard released a request for information (RFI) July 18 to gather market research for the Coast Guard Cutter Polar Star service life extension project (SLEP) as part of the In-Service Vessel Sustainment Program (ISVS). The SLEP effort will recapitalize a number of major systems – including machinery control and propulsion power distribution systems – and extend the service life of the cutter by four years. The work will include a six-month long lead time material procurement and detailed design phase, followed by a minimum of three annual repair execution phases between 2021 and 2024.

The RFI is available here.

Polar Star, the Coast Guard’s only active heavy icebreaker, was commissioned in 1976. The 399-foot ship is currently responsible for nine of the 11 Coast Guard statutory missions. Each winter, the cutter travels to McMurdo Station in Antarctica as part of Operation Deep Freeze, which supports the National Science Foundation-managed U.S. Antarctic Program.

“The SLEP for Polar Star is essential to maintain year-round access to the polar regions until new heavy polar icebreakers are delivered,” said Ken King, program manager for the ISVS program. “The challenge for this program will be to balance phased SLEP work with continued Polar Star operational deployments.”

The deadline to submit responses is Aug. 3, 2018 at 4 p.m. EDT.

For more information: In-Service Vessel Sustainment program page